A high rise building is usually characterized by its changing layout from basement to roof, with repeating structures in cores, staircases, shear walls, columns and slabs. Basement walls often require a single side supported shutter system with straight or circular wall formwork. The slabs are individually formed using a system like Multiflex, due to the closed façades. Panelised slab system is also an option when early striking is a must and shifting by crane is impossible.

 

Especially shear walls, columns change shape throughout the project duration. In this case, the more versatile panel system with built-in plywood, such as TriTec, is used at the beginning until the sections become typical or repeating all the way through. However, the concrete finish specifications of the entire structure should be taken into consideration. Beam/waler wall systems like Flex 50 with plywood chosen by site might provide fair face concrete finish.  But this requires considerable manpower in customizing the wall shutter for the next pour.
Detaching the building of cores and staircases from the remaining project is the usual practice for high rises with more than six floors to be built. Up to 12 storeys, the utilization of crane-dependent climbing formwork CS240 is most economical. Depending on storage area at site and/or if the building exceeds 12 floors, hydraulic automatic climbing formwork is  in demand. Huge core walls and concreted facades indicate the usage as well. In any case, construction work becomes safer regardless of weather conditions. In conjunction with climbing scaffold, beam/waler wall formwork is used, such as Flex 50 (straight/round). For smaller projects, panelised systems like TriTec or TriTec Light for shafts might be an option.For safe working, additional platforms are needed especially at slab edges.  GHI recommends the installation of CS240/CS180 working platforms.  These are affordable and well-proven solutions. 
Limits in cranage, special reinforcements like beams and clearing heights exceeding 5.90 m require more individual solutions in the slab of the basements, first, mezzanine and technical floors. In here, the light weight and versatile Multiflex slab superstructure is used with individual support (either telescopic props or heavy duty shoring towers D-15). Open facades, uncomplicated and large areas allow the use of pre-assembled Multiflex slab formwork into “Table Units.” With appropriate shifting gear, the table units are lifted to the next floor after striking. This is most economical and fast solution available in the market.  The GHI lifting fork with a vertical member is suitable to lift the table out of the open building when the floor right above remains with shutter.
Panelised decking systems allow early striking after two days, while the slab has to remain under shutter for at least seven days. Props with drop heads remain under the slab until required concrete strength is achieved and the shutter panels itself are moved to the next floor. Large, uncomplicated slab areas and limits in cranage indicate the economical use of these systems.
GHI formwork systems are designed and manufactured to finish a complete floor within a one-week cycle.

 

High Rise
Novotel & Ibis Hotels & Novotel Serviced Apartment - Fujairah, UAE
High Rise
Section - CS240 climbing system for Jeddah Corniche Tower
High Rise
Section - Flex 50 circular core wall for Jeddah Corniche Tower
High Rise
Layout & Section - D-15 shoring and Tableform slab for Jeddah Corniche Tower
High Rise
Layout & Section - Multiflex slab & D-15 shoring for Jeddah Corniche Tower
High Rise
Corniche Tower - Jeddah, Saudi Arabia
High Rise
Section - Flex 50 shear wall for Jeddah Corniche Tower
High Rise
Layout & Section - Multiflex slab formwork for Bridge Tower
High Rise
Bridge Tower - Dubai, UAE
High Rise
B2B Tower - Dubai, Core Wall Formwork with Tritec System
High Rise
B2B Tower - Slab with D15 Towers
High Rise
B2B Tower - Dubai, UAE
High Rise
Novotel & Ibis Hotels - SB Supporting Brace Frames Stage I
High Rise
Novotel & Ibis Hotels - SB Supporting Brace Frames Stage II
High Rise
Novotel & Ibis Hotels - Flex 50 staircases and lift shaft formwork
High Rise
Novotel & Ibis Hotels - Flex 50 basement column formwork
High Rise
Layout & Section for Tableform slab formwork - Novotel & Ibis Hotels
High Rise
High Rise